Laindon Community Centre - Works timeline and planned reopening

Basildon Council is now fully committed to reopening Laindon Community Centre as soon as works to ensure the centre is fit for purpose have been completed.

Basildon Council took over the running of Laindon Community Centre in November 2020 after the keys were handed to the council by the Laindon Community Association.

Following a thorough buildings inspection it was discovered the centre was no longer fit for purpose. Works are currently underway to bring the building back into use and ensure it is fit for purpose and meets the needs of the community.

This is provisional timeline and further progress updates will be published here as time goes on.

Works timeline and planned reopening as at 08 July 2021

Completion date  / notesActionStatus
May 2021

Laindon Community Centre Condition Survey - Report review

Completed
18  June 2021

Review of Mechanical Services by Ridge (consultants)

Completed
02 July 2021

Asbestos R&D Survey(Legal requirement for a survey to be undertaken prior to any works commencing)

In Progress
09 July 2021Asbestos removal works arising from survey (if any)Works (if any) yet to start

09 July 2021

Scope and fee price received and work now to be commissioned

Scope of works report on Mechanical Services:
  • Liaise with gas utility provider and generate a quotation for a re-connection/New connection
  • Generate a scope of works and any drawings.
Proposed Mechanical works:
  • Reconnection of gas, drain and power flush the heating system fill and dose, re-commission the existing boilers, pumps, pressurisation unit, controls, etc.
Review options to convert the water system to mains fed and scope accordingly.

Proposed Electrical works:
  • Isolate and test the incoming supply and main distribution. Test emergency lighting, fire alarm, intruder alarm, etc. carryout a small power test and inspection.

In relation with a shortlisted contractor provide a quotation for the works.

With the quotation approved appoint the contractor and plan the works.

In Progress

16 July 2021

6-8 weeks work

Morgan Sindall Property Services commissioned to undertake Phase 1 works with Framework contractor:

a) Fire safety works - Includes Fire Compartmentalisation and fire doors, (Subject to availability of fire doors) work to commence mid-July

Commissioning in Progress

Mid-end of August

8 weeks work

b) Water safety works and remaining package of works etc.- Legionella works and accessible toilet facilities works

In Progress

Mid-September

4 weeks work

c) Reconnection of gas (10-12 week lead potentially) - To start after fire safety works complete and insurers content to allow reconnection

Works yet to start
End of SeptemberReopeningDate to be announced